Consider approval to upgrade/replace the raised access flooring in the City of Griffin Data Center by lowest bidder JLJ and Associates, in the amount of $24,000.00. Jack Poland, Chief Information Officer, Information Technology, will address.
SPECIAL CONSIDERATIONS OR CONCERNS: |
The City of Griffin Data Center raised floor needs upgraded with new panels, stringers and pedestals. The current flooring is over 40 years old and has become hazardous to walking traffic. The new flooring will provide stronger support for all IT equipment to include the server racks and Uninterrupted Power Supply (UPS).
Staff recommends approval to purchase the new raised access flooring.
Funding for the purchase comes from FY17 budget of $25,000.00. Three estimates were obtained with the lowest quoted attached. |