AGENDA ITEM SUMMARY
Consider approval to reject all bids for construction of North Griffin Revitalization Area - Zone 6 Project, City of Griffin Community Development Block Grant and rebid project. Public Works and Utilities Director Brant D. Keller will address.
SPECIAL CONSIDERATIONS OR CONCERNS: |
Community Development Block Grants have 3 components in each grant. They consist of engineering, grant administration and construction. Engineering and grant administration are within budget. The construction bid was not when the bids were opened. The amount budgeted for construction was $578,282.00. PCG has revised the schedule and will be rebidding the construction phase of the CDBG VI grant.
Staff recommends approval.
Funds for project: $500,000.00 CDBG and City Match is 227,007.00 totaling $727,007.00 for the project. Construction to be rebid. |