| AGENDA ITEM SUMMARY
Approve a change order to the contract with Renfroe Construction in the amount of $188,324.01 for the construction of the new Electric Operations facilities. Electric Director Bill Bosch will address.
SPECIAL CONSIDERATIONS OR CONCERNS: |
This is required to cover the cost to remove rock required by the relocation of the detention pond and to install the water line, and for other minor revisions to the project.
Staff recommends approval
The approved budget for this project was $2.645 million with an $50,000 contingency. With this change order, the Renfroe contract will come in $2,485,442.01, and furnishings are approved at $70,859.03, bringing the total project cost in at $2,556,301.04, which is $143,698.96 under budget. | | | |