AGENDA ITEM SUMMARY
Consider approval to hire low bidder Four Seasons Cable Construction to install road and creek bores in the Lakes of Green Valley Industrial Park in the amount of $63,178.80. Electric Director Bill Bosch will address. Approved
SPECIAL CONSIDERATIONS OR CONCERNS: |
Due to existing roadway and natural gas pipeline obstacles, it is necessary to bore to complete the installation of underground primary within the Lakes of Green Valley Industrial Park. There are only two known bore contractors in this area capable of installing the size bore required. This quote includes labor, materials and site restoration.
Staff recommends approval.
This will be funded by the Electric Department's approved 2014-2015 Capital Project Budget, The Lakes at Green Valley (Feeder Additions). |