Consider approval of lowest and most responsive bid from Mosley Tractor and Supply to refurbish the under carriage of the D155 Komatsu Dozier for the Shoal Creek Landfill in the amount of $27,142.52.  Central Services Director Phill Francis will address.   Approved


SPECIAL CONSIDERATIONS OR CONCERNS:

This is a scheduled and budgeted F/Y 14-15 expense as detailed in the attachment. Refurbishing of Dozier undercarriages are scheduled based on manufacturer specifications and pre- determined wear limits to prevent catastrophic failure of track and drivetrain components.

Per COG purchasing protocol, three quotes were submitted and Mosley Tractor was the lowest bid considered that encompassed the repair/refurbishing standard required.



STAFF RECOMMENDATION:

Staff recommends approval. 

FINANCIAL IMPACT:

Budgeted Expense ________________ $34,000.00

 

Actual Quoted Expense ____________ $27,142.52

 

Net Positive Effect to F/Y 14-15 Budget $6,857.48