Item Coversheet

AGENDA ITEM SUMMARY

ITEM SUMMARY:

Consider option #1 or option #2 and approve the concept for the LCI design as presented in the Georgia Department of Transportation letter dated September 25, 2014. for the Public Works and Utilities Department.   Dr. Brant D. Keller will address.  Tabled until future date


SPECIAL CONSIDERATIONS OR CONCERNS:

Option #1 - Leave current configuration of GA 155 and share one lane as a bike lane. GDOT will at their expense install turn signal at N. Hill Street and Broadway.

 

Option #2 - Reduce road diet to one lane with a dedicated bike land and buffer strip and extend parking places 3 feet with the condition that GDOT can some time in the future make intersection improvements if traffic becomes congested. GDOT will at their expense install turn signal at N. Hill and Broadway.



STAFF RECOMMENDATION:

Staff will move forward on Commissions direction.

FINANCIAL IMPACT:

Project has been budgeted in 2008 SPLOST.

ATTACHMENTS:
File NameDescription
GDOT_Letter_09.25.14.pdfDowntown LCI
Submitted by:

Meeting Date:

Brant D. Keller PhD

11/25/2014

Reviewed by:

 
Kenny L. Smith, City Manager