Item Coversheet

AGENDA ITEM SUMMARY

ITEM SUMMARY:

Consider amendment to existing Potato Creek Wastewater Treatment Plant design and expansion task order with Paragon Consulting Group to design a copper treatment process to meet new permit limits in the amount of $199,990.00 for the Water and Wastewater Department.  Director of the Public Works and Utilities Dr. Brant D. Keller will address.  Approved


SPECIAL CONSIDERATIONS OR CONCERNS:

Paragon Consulting Group is currently making engineering changes to the Potato Creek WWTP upgrade and expansion. The City of Griffin received its wastewater NPDES Permit 2014 from GAEPD and our limits for discharge have been reduced significantly therefore in the plant upgrade we must include a process to remove copper from our discharge to meet water quality standards. It is going to require a chemical treatment process design and this process will be incorporated in the plant construction.

STAFF RECOMMENDATION:

Staff recommends approval.

FINANCIAL IMPACT:

The amount of this TOF/amendment is $199,990.00. Funding to come from the Capital Cost Recovery Fee, Industrial Development Authority Check and the CWSRF Loan.

ATTACHMENTS:
File NameDescription
2014_August_5_TOF_Amendment_Copper_Treatment.pdfPCWWTP Copper Design
Submitted by:

Meeting Date:

Brant D. Keller PhD

8/12/2014

Reviewed by:

 
Brant D. Keller PhD