Item Coversheet

AGENDA ITEM SUMMARY

ITEM SUMMARY:

Consider approval of a Task Order for the Pre-Engineering of Community Development Block Grant to Paragon Consulting Group for Phase VII-VIII in the amount of $6,700.00 for the Water and Wastewater Department.  Director of Public Works and Utilities Dr. Brant D. Keller will address.  Approved


SPECIAL CONSIDERATIONS OR CONCERNS:

This is for the last phases of the CDBG grants for the Thomaston Mill Village repair or replacement of water and wastewater infrastructure.

STAFF RECOMMENDATION:

Staff recommends approval.

FINANCIAL IMPACT:

Budget FY2014-2015 Account 505-4405-52-1200 in amount $18,500.00. Amount of this TOF is $6,700.00

ATTACHMENTS:
File NameDescription
PCG_TOF_Pre_Eng_CDBG_VI-VIII.pdfPre-Eng CDBG VII-VIII
Submitted by:

Meeting Date:

Brant D. Keller PhD

8/12/2014

Reviewed by:

 
Brant D. Keller PhD