AGENDA ITEM SUMMARY
Consider a contract with Renfroe Construction Company, LLC, the lowest and most responsive bidder, for the construction of the Griffin Power Maintenance facility to be constructed on the Thomas Packing Property. The contract price is $2,297,118 with a $50,000 contingency. Director of Electric Bill Bosch will address. Approved
SPECIAL CONSIDERATIONS OR CONCERNS: |
The approved budget for this project is $2.7 million. A separate agenda item for furnishings in the amount of approximately $100,000 will be submitted at a later date. These combined agreements will bring the project around $300,000 under budget.
Staff recommends approval.
Funding for the project will come from the City's Municipal Competitive Trust, Short Term Portfolio. This Trust account will be reduced by approximately $2,397,118 by the completion of the project. |