Item Coversheet

AGENDA ITEM SUMMARY

ITEM SUMMARY:

Consider approval of the upgrade and install of fiber by Four Seasons Cable to substation 8 across from The Lakes at Green Valley for the cost of $27,000.

Electric Director Bill Bosch will address.




SPECIAL CONSIDERATIONS OR CONCERNS:

The selection of Four Seasons was based on using this vendor for recent similar projects at our sub 1 and sub 4 locations. This is a continuation of the same work to our future largest substation. We have also used Netplanner for other fiber projects in the City but, with the specialized nature of this work, we felt it important to continue with an experienced, proven vendor with a successful track record for other similar projects.



STAFF RECOMMENDATION:

Staff recommends approval.



FINANCIAL IMPACT:

This  $27,000 upgrade to the fiber path will also provide bandwidth to new industrial customers, resulting in improved functionality while providing the possibility of new data revenue from future industrial customers, and enhanced communication to substation 8. 

ATTACHMENTS:
File NameDescription
Fiber_to_Sub_Station_No_8.pdfSub 8 fiber quote
Submitted by:

Meeting Date:

Bill Bosch

2/9/2016

Reviewed by:

 
Kenny L. Smith