AGENDA ITEM SUMMARY

ITEM SUMMARY:

Consider approval of a Task Order to Paragon Consulting Group for Surveying, Engineering and Construction Management for the Community Development Block Grant Phase VII of the Thomaston Mill Village in the amount of $72,883.00 for the Water and Wastewater Department of the Public Works and Utilities Department. Director of Public Works and Utilities Brant D. Keller will address.


SPECIAL CONSIDERATIONS OR CONCERNS:

This concludes the final phase of the water and sewer improvements in the Thomaston Mill Village project. The following numbers are cumulative for the project: DCA funding is $3,500,000.00 and City of Griffin funding is $1,870,125 for a total of $5,370,125. The project was for 7.1 miles of water main replaced, 2.3 miles of sewer main replaced or rehabilitated, 42 new hydrants installed, 53 sewer manholes added or rehabilitated, and 497 water service connections replaced.

STAFF RECOMMENDATION:

Staff recommends approval.

FINANCIAL IMPACT:

Budget FY2015-2016 in the amount of $668,528.00 227-4000-54-1400-1. Amount of this TOF is $72,883.00

ATTACHMENTS:
File NameDescription
PCG_TOF_Engineering_CDBG_VII.pdfPCG TOF Engineering CDBG VII
Submitted by:

Meeting Date:

Brant D. Keller

9/8/2015

Reviewed by:

 
Kenny L. Smith